BM522 Project Management CW1 Sample Answer: Regent House Hotel Digital Check-In Project Plan

For information and reference only – not to be submitted as your own work.

This extract shows one way to answer the BM522 Project Management CW1 Regent House Hotel digital check-in brief at Buckinghamshire New University. It covers the business case, the network diagram calculations, a Gantt summary, the WBS, the risk register and the quality criteria. All figures other than those given in the brief are illustrative. For the thinking behind each choice, read our BM522 CW1 critical path and Gantt guide.

Planning table

Task Suggested share of the 1,500 words What markers look for
1. Business case, objectives, method about 350 A clear need, three SMART objectives, constraints and a justified approach
2. Network diagram, critical path, Gantt about 250 plus diagrams Correct forward and backward pass, one stated completion time, dated milestones
3. Stakeholders and communication about 250 Five or more stakeholders placed on a power and interest grid
4. Work breakdown structure about 100 plus diagram Deliverables, numbered levels, no chronological list
5. Risk analysis about 250 Scored risks, owners and mitigation for the top five
6. Quality about 200 Five requirements with acceptance criteria and control measures

Task 1: Business case and objectives

The Regent House Hotel loses guest goodwill when paper registration, identity checks and key allocation create queues on busy Friday and Saturday afternoons. The aim is to replace manual check-in with a digital system for pre-arrival registration, secure identity upload, payment confirmation, digital or kiosk room access and self-service check-out, within the approved budget of £180,000 and six months from 11 January 2027.

Three SMART objectives frame the project (illustrative targets):

  • Cut average check-in time from about eight minutes to under three minutes for at least 70% of guests by the end of the pilot.
  • Complete integration with the Property Management System and pass the data protection review before internal testing ends.
  • Deliver full rollout by 18 May 2027 within the £180,000 budget, with no more than one hour of unplanned front-desk downtime.

The project is a predictable, plan-driven delivery with a fixed scope, a single supplier and strong dependencies, so a predictive (waterfall-style) approach with stage gates suits it better than an agile one (APM, 2019; PMI, 2021). Agile techniques can still help inside the pilot, where guest feedback is collected and small fixes are released quickly.

Buy Non Plagiarized & Properly Structured Assignment Solution

Task 2: Network diagram and critical path

The table applies the forward and backward pass using the day 0 convention given in the brief, so activity 1 starts at day 0. Early finish equals early start plus duration. Late start equals late finish minus duration. Total float is late start minus early start.

ID Days ES EF LS LF Float
1 2 0 2 0 2 0
2 7 2 9 2 9 0
3 5 9 14 9 14 0
4 2 14 16 14 16 0
5 4 16 20 16 20 0
6 10 20 30 20 30 0
7 8 30 38 30 38 0
8 3 38 41 38 41 0
9 5 16 21 36 41 20
10 6 16 22 35 41 19
11 10 41 51 41 51 0
12 8 51 59 51 59 0
13 6 51 57 53 59 2
14 6 41 47 53 59 12
15 10 59 69 59 69 0
16 7 69 76 69 76 0
17 12 76 88 76 88 0
18 4 88 92 88 92 0

The critical path is 1 → 2 → 3 → 4 → 5 → 6 → 7 → 8 → 11 → 12 → 15 → 16 → 17 → 18, with a shortest completion time of 92 working days. Three points deserve a sentence in the report. Activity 11 starts at day 41 because it waits for the latest of activities 8 (day 41), 9 (day 21) and 10 (day 22). Activity 15 starts at day 59 because integration (activity 12, finishing at day 59) outlasts the data protection review (activity 13, day 57) and the kiosk installation (activity 14, day 47). Activity 16 follows activity 15 at day 69, not activity 10 at day 22. Activity 13 has only two days of float, so it is a near-critical path that needs watching (Kelley and Walker, 1959).

Counting 92 working days from Monday 11 January 2027, and ignoring public holidays as the brief instructs, project closure falls on Tuesday 18 May 2027, comfortably inside six months. The Gantt chart then uses the same dates:

Milestone (illustrative) Linked activity Working-day finish Date
Senior management approval 4 16 1 February 2027
Supplier contract signed off 8 41 8 March 2027
Integration complete 12 59 1 April 2027
Internal testing complete 15 69 15 April 2027
Staff trained 16 76 26 April 2027
Pilot reviewed 17 88 12 May 2027
Rollout and closure 18 92 18 May 2027

In MS Project, enter the durations as working days, link the predecessors exactly as in the brief, and let the software confirm that the critical tasks match your hand calculation.

Task 3: Stakeholders and communication

Stakeholder Power Interest Strategy
General manager (sponsor) High High Manage closely; fortnightly highlight report
Data protection officer High Medium Consult at design; sign-off before testing
Front-office manager and reception staff Medium High Involve in design and training; address job concerns early
Software supplier Medium High Weekly delivery meeting under the contract
Pilot guests Low Medium Keep informed; short feedback survey

A likely conflict is between the finance manager, who wants cost control, and the front-office manager, who may ask for extra kiosks. The communication plan in the appendix should state the audience, message, channel, frequency and owner for each group.

Task 4: Work breakdown structure

A deliverable-based WBS groups outputs rather than tasks: 1.0 Project management (mandate, business case, reports, closure); 2.0 Requirements and design (requirements document, guest journey, technical assessment); 3.0 Procurement (specification, evaluation report, signed contract); 4.0 System build (configured platform, PMS integration, kiosks and tablets); 5.0 Compliance (data protection impact assessment, payment security confirmation); 6.0 Testing and readiness (test report, operating procedures, trained staff); 7.0 Launch (pilot report, rollout).

Task 5: Risk analysis

Risk Likelihood (1-5) Impact (1-5) Score Mitigation
PMS integration fails or is delayed 4 5 20 Early interface test; supplier penalty clause; reserve in the budget
Guest data breach 3 5 15 Encryption, role-based access, penetration test before pilot
Supplier delay 3 4 12 Milestone payments; fallback shortlisted supplier
Staff resistance 3 4 12 Early involvement, training, visible management support
Front-office disruption during cut-over 2 5 10 Run pilot on quieter days; keep manual fallback

Scores are likelihood multiplied by impact. Under the UK GDPR, identity documents and payment-related data must be handled with appropriate security and a lawful basis, which is why the data protection review sits on the path to testing (Information Commissioner’s Office, no date).

Task 6: Quality requirements

Requirement Acceptance criterion (illustrative) Control
Speed Check-in completes in under three minutes for 70% of pilot guests Timed pilot sample
Accuracy No more than 1 in 200 records mismatched with the PMS Daily reconciliation report
Availability 99.5% uptime during the pilot Supplier monitoring log
Security No critical findings in the security test Independent test and retest
Usability At least 80% of guests rate the process as easy Feedback survey

If you would rather have help checking your own critical path and WBS, our project management assignment help team can review your draft, and our risk management assignment help page covers risk registers. You can also submit your assignment brief for a quote.

Please Write Fresh Non Plagiarized Assignment on this Topic

References

Association for Project Management (2019) APM body of knowledge. 7th edn. Princes Risborough: Association for Project Management.

Information Commissioner’s Office (no date) UK GDPR guidance and resources. Available at: https://ico.org.uk/for-organisations/uk-gdpr-guidance-and-resources/ (Accessed: 16 November 2026).

Kelley, J.E. and Walker, M.R. (1959) ‘Critical-path planning and scheduling’, Proceedings of the Eastern Joint Computer Conference, Boston, 1-3 December, pp. 160-173.

Project Management Institute (2021) A guide to the project management body of knowledge (PMBOK guide) and the standard for project management. 7th edn. Newtown Square, PA: Project Management Institute.

Prepared by
Students Assignment Help UK Editorial Team

Students Assignment Help UK Editorial Team

This model answer was prepared by our editorial team in response to a real assignment brief we received. It shows one way to approach the task and is meant as a study guide, not for submission.

do you want plagiarism free & researched assignment solution!

UPTO 35% DISCOUNT

Get Your Assignment Completed At Lower Prices

Plagiarism Free Solutions
100% Original Work
24*7 Online Assistance
Native PhD Experts
Hire a Writer Now

Facing Issues with Assignments? Talk to Our Experts Now!Download Our App Now!

Have Questions About Our Services?
Download Our App!

Get the App Today!

QRcode