- Project Management Assignment Sample UK
- EFIM30014 Operations Management UOB Assignment Answer UK
- MGRC30003 Decision Analysis and Simulation UOB Assignment Answer UK
- EFIM30030 Strategy UOB Assignment Answer UK
- EFIM30021 Portfolio Management UOB Assignment Answer UK
- SWOT Analysis of Barclays, UK
- EFIM20026 Organisation Theory Assignment Answer UK
- EFIM20022 People, Work and Organisations Assignment Answer UK
- EFIM20019 Public Management Assignment Answer UK
- EFIM20005 Management Science Assignment Answer UK
- 08 25676 Professional Development Assignment Answer UK
- 07 32181 Decision Making and Control Assignment Answer UK
- BGXC001 Developing a coaching culture Assignment Sample UK
- B329 Leadership In A Changing World Assignment Sample UK
- BGXC004 Developing strategy to manage uncertainty Assignment Sample UK
- BGXS001 Introduction to business and workplace coaching Assignment Sample UK
- B208 Developing leadership Assignment Sample UK
- BU7002 Management Research Method Assignment Sample UK
- BU7030 Managing Innovation Assignment Sample UK
- BU7039 Understanding And Managing People Assignment Sample UK
BM522 Project Management CW1 Sample Answer: Regent House Hotel Digital Check-In Project Plan
For information and reference only – not to be submitted as your own work.
This extract shows one way to answer the BM522 Project Management CW1 Regent House Hotel digital check-in brief at Buckinghamshire New University. It covers the business case, the network diagram calculations, a Gantt summary, the WBS, the risk register and the quality criteria. All figures other than those given in the brief are illustrative. For the thinking behind each choice, read our BM522 CW1 critical path and Gantt guide.
Planning table
| Task | Suggested share of the 1,500 words | What markers look for |
|---|---|---|
| 1. Business case, objectives, method | about 350 | A clear need, three SMART objectives, constraints and a justified approach |
| 2. Network diagram, critical path, Gantt | about 250 plus diagrams | Correct forward and backward pass, one stated completion time, dated milestones |
| 3. Stakeholders and communication | about 250 | Five or more stakeholders placed on a power and interest grid |
| 4. Work breakdown structure | about 100 plus diagram | Deliverables, numbered levels, no chronological list |
| 5. Risk analysis | about 250 | Scored risks, owners and mitigation for the top five |
| 6. Quality | about 200 | Five requirements with acceptance criteria and control measures |
Task 1: Business case and objectives
The Regent House Hotel loses guest goodwill when paper registration, identity checks and key allocation create queues on busy Friday and Saturday afternoons. The aim is to replace manual check-in with a digital system for pre-arrival registration, secure identity upload, payment confirmation, digital or kiosk room access and self-service check-out, within the approved budget of £180,000 and six months from 11 January 2027.
Three SMART objectives frame the project (illustrative targets):
- Cut average check-in time from about eight minutes to under three minutes for at least 70% of guests by the end of the pilot.
- Complete integration with the Property Management System and pass the data protection review before internal testing ends.
- Deliver full rollout by 18 May 2027 within the £180,000 budget, with no more than one hour of unplanned front-desk downtime.
The project is a predictable, plan-driven delivery with a fixed scope, a single supplier and strong dependencies, so a predictive (waterfall-style) approach with stage gates suits it better than an agile one (APM, 2019; PMI, 2021). Agile techniques can still help inside the pilot, where guest feedback is collected and small fixes are released quickly.
Buy Non Plagiarized & Properly Structured Assignment Solution
Task 2: Network diagram and critical path
The table applies the forward and backward pass using the day 0 convention given in the brief, so activity 1 starts at day 0. Early finish equals early start plus duration. Late start equals late finish minus duration. Total float is late start minus early start.
| ID | Days | ES | EF | LS | LF | Float |
|---|---|---|---|---|---|---|
| 1 | 2 | 0 | 2 | 0 | 2 | 0 |
| 2 | 7 | 2 | 9 | 2 | 9 | 0 |
| 3 | 5 | 9 | 14 | 9 | 14 | 0 |
| 4 | 2 | 14 | 16 | 14 | 16 | 0 |
| 5 | 4 | 16 | 20 | 16 | 20 | 0 |
| 6 | 10 | 20 | 30 | 20 | 30 | 0 |
| 7 | 8 | 30 | 38 | 30 | 38 | 0 |
| 8 | 3 | 38 | 41 | 38 | 41 | 0 |
| 9 | 5 | 16 | 21 | 36 | 41 | 20 |
| 10 | 6 | 16 | 22 | 35 | 41 | 19 |
| 11 | 10 | 41 | 51 | 41 | 51 | 0 |
| 12 | 8 | 51 | 59 | 51 | 59 | 0 |
| 13 | 6 | 51 | 57 | 53 | 59 | 2 |
| 14 | 6 | 41 | 47 | 53 | 59 | 12 |
| 15 | 10 | 59 | 69 | 59 | 69 | 0 |
| 16 | 7 | 69 | 76 | 69 | 76 | 0 |
| 17 | 12 | 76 | 88 | 76 | 88 | 0 |
| 18 | 4 | 88 | 92 | 88 | 92 | 0 |
The critical path is 1 → 2 → 3 → 4 → 5 → 6 → 7 → 8 → 11 → 12 → 15 → 16 → 17 → 18, with a shortest completion time of 92 working days. Three points deserve a sentence in the report. Activity 11 starts at day 41 because it waits for the latest of activities 8 (day 41), 9 (day 21) and 10 (day 22). Activity 15 starts at day 59 because integration (activity 12, finishing at day 59) outlasts the data protection review (activity 13, day 57) and the kiosk installation (activity 14, day 47). Activity 16 follows activity 15 at day 69, not activity 10 at day 22. Activity 13 has only two days of float, so it is a near-critical path that needs watching (Kelley and Walker, 1959).
Counting 92 working days from Monday 11 January 2027, and ignoring public holidays as the brief instructs, project closure falls on Tuesday 18 May 2027, comfortably inside six months. The Gantt chart then uses the same dates:
| Milestone (illustrative) | Linked activity | Working-day finish | Date |
|---|---|---|---|
| Senior management approval | 4 | 16 | 1 February 2027 |
| Supplier contract signed off | 8 | 41 | 8 March 2027 |
| Integration complete | 12 | 59 | 1 April 2027 |
| Internal testing complete | 15 | 69 | 15 April 2027 |
| Staff trained | 16 | 76 | 26 April 2027 |
| Pilot reviewed | 17 | 88 | 12 May 2027 |
| Rollout and closure | 18 | 92 | 18 May 2027 |
In MS Project, enter the durations as working days, link the predecessors exactly as in the brief, and let the software confirm that the critical tasks match your hand calculation.
Task 3: Stakeholders and communication
| Stakeholder | Power | Interest | Strategy |
|---|---|---|---|
| General manager (sponsor) | High | High | Manage closely; fortnightly highlight report |
| Data protection officer | High | Medium | Consult at design; sign-off before testing |
| Front-office manager and reception staff | Medium | High | Involve in design and training; address job concerns early |
| Software supplier | Medium | High | Weekly delivery meeting under the contract |
| Pilot guests | Low | Medium | Keep informed; short feedback survey |
A likely conflict is between the finance manager, who wants cost control, and the front-office manager, who may ask for extra kiosks. The communication plan in the appendix should state the audience, message, channel, frequency and owner for each group.
Task 4: Work breakdown structure
A deliverable-based WBS groups outputs rather than tasks: 1.0 Project management (mandate, business case, reports, closure); 2.0 Requirements and design (requirements document, guest journey, technical assessment); 3.0 Procurement (specification, evaluation report, signed contract); 4.0 System build (configured platform, PMS integration, kiosks and tablets); 5.0 Compliance (data protection impact assessment, payment security confirmation); 6.0 Testing and readiness (test report, operating procedures, trained staff); 7.0 Launch (pilot report, rollout).
Task 5: Risk analysis
| Risk | Likelihood (1-5) | Impact (1-5) | Score | Mitigation |
|---|---|---|---|---|
| PMS integration fails or is delayed | 4 | 5 | 20 | Early interface test; supplier penalty clause; reserve in the budget |
| Guest data breach | 3 | 5 | 15 | Encryption, role-based access, penetration test before pilot |
| Supplier delay | 3 | 4 | 12 | Milestone payments; fallback shortlisted supplier |
| Staff resistance | 3 | 4 | 12 | Early involvement, training, visible management support |
| Front-office disruption during cut-over | 2 | 5 | 10 | Run pilot on quieter days; keep manual fallback |
Scores are likelihood multiplied by impact. Under the UK GDPR, identity documents and payment-related data must be handled with appropriate security and a lawful basis, which is why the data protection review sits on the path to testing (Information Commissioner’s Office, no date).
Task 6: Quality requirements
| Requirement | Acceptance criterion (illustrative) | Control |
|---|---|---|
| Speed | Check-in completes in under three minutes for 70% of pilot guests | Timed pilot sample |
| Accuracy | No more than 1 in 200 records mismatched with the PMS | Daily reconciliation report |
| Availability | 99.5% uptime during the pilot | Supplier monitoring log |
| Security | No critical findings in the security test | Independent test and retest |
| Usability | At least 80% of guests rate the process as easy | Feedback survey |
If you would rather have help checking your own critical path and WBS, our project management assignment help team can review your draft, and our risk management assignment help page covers risk registers. You can also submit your assignment brief for a quote.
Please Write Fresh Non Plagiarized Assignment on this Topic
References
Association for Project Management (2019) APM body of knowledge. 7th edn. Princes Risborough: Association for Project Management.
Information Commissioner’s Office (no date) UK GDPR guidance and resources. Available at: https://ico.org.uk/for-organisations/uk-gdpr-guidance-and-resources/ (Accessed: 16 November 2026).
Kelley, J.E. and Walker, M.R. (1959) ‘Critical-path planning and scheduling’, Proceedings of the Eastern Joint Computer Conference, Boston, 1-3 December, pp. 160-173.
Project Management Institute (2021) A guide to the project management body of knowledge (PMBOK guide) and the standard for project management. 7th edn. Newtown Square, PA: Project Management Institute.