BM522 Project Management CW1 Assignment Brief 2026-27: Regent House Hotel Digital Guest Check-In Project Report | Buckinghamshire New University

BM522 Project Management – CW1 Individual Project Report: The Regent House Hotel Digital Guest Check-In Project

University Buckinghamshire New University (Level 5, C23 framework)
Module BM522 Project Management
Assessment CW1 – 1,500-word individual project report
Weighting 50%
Deadline Saturday 14 November 2026, before 2:00 pm
AI status Non-secure: reasonable and appropriate AI use permitted

BM522 CW1 gives students a ready-made project and a full activity list, then asks them to plan it like a project manager: business case and SMART objectives, a network diagram with the critical path, a Gantt chart, stakeholders, a WBS, a risk register and quality criteria.

Project Scenario (summary)

The Regent House Hotel is a privately owned 85-room boutique hotel in Belfast serving business travellers and weekend tourists. Manual paper registration, identity checks, payment verification and key allocation cause long queues between 3 pm and 6 pm on Fridays, Saturdays and event dates. Management has approved a digital guest check-in and check-out system with pre-arrival registration, secure ID upload, payment confirmation, digital or kiosk room access, self-service check-out and automated receipts. Scope includes platform procurement and configuration, integration with the Property Management System, kiosks or tablets, staff training, a GDPR and data security review, pilot testing and full rollout.

  • Start: Monday 11 January 2027; full rollout before the summer season, within six months
  • Indicative budget: £180,000; minimum disruption to hotel operations
  • Key risks: integration issues, staff resistance, guest data privacy, supplier delays, cybersecurity and front-office disruption
  • Team: general manager, front-office manager, IT support, finance manager, data protection officer, external software supplier, reception staff representatives and pilot guest users

Activity Scheduling Information

ID Task Days Predecessors
1 Approve project mandate and appoint project manager 2 –
2 Review current front-office process and identify requirements 7 1
3 Prepare business case and project initiation document 5 2
4 Obtain approval from hotel senior management 2 3
5 Prepare supplier specification and request for proposal 4 4
6 Invite suppliers and receive proposals 10 5
7 Evaluate proposals, select supplier and negotiate contract 8 6
8 Complete contract approval and procurement sign-off 3 7
9 Conduct technical assessment of existing hotel systems 5 4
10 Design digital check-in process and guest journey 6 4
11 Configure digital check-in software 10 8, 9, 10
12 Integrate system with existing Property Management System 8 11
13 Complete GDPR, data security and payment compliance review 6 11
14 Install guest self-service kiosks and/or tablet devices 6 8, 9
15 Conduct internal testing and resolve technical issues 10 12, 13, 14
16 Develop operating procedures and train front-office staff 7 10, 15
17 Run pilot launch, review feedback and implement improvements 12 16
18 Full system rollout and project closure report 4 17

All durations are working days (Monday–Friday, eight hours per day; weekends excluded, public holidays ignored). Network diagram calculations use the day 0 convention.

Coursework Tasks

  1. Task 1 – Business case, project objectives and methodology [15 marks]: business need and aim, three SMART objectives, deliverables, milestones, outcomes and benefits, time/cost/operational constraints, and a briefly justified planning approach.
  2. Task 2 – Network diagram, critical path and Gantt chart [25 marks]: (i) a network diagram showing all activities, dependencies, durations, ES, LS, EF and LF, with the critical path highlighted and the shortest completion time stated; (ii) a Gantt chart in MS Project or an approved tool showing sequence, dependencies, dates and milestones.
  3. Task 3 – Stakeholder analysis and communication strategies [20 marks]: at least five internal and external stakeholders on a power/interest matrix, their expectations, concerns, influence and likely conflicts, plus a communication plan in the appendix.
  4. Task 4 – Work Breakdown Structure [10 marks]: a clearly numbered, deliverable-oriented WBS (not a chronological activity list).
  5. Task 5 – Risk analysis: a risk register with mitigation strategies for the five highest-priority risks.
  6. Task 6 – Quality: five quality requirements with acceptance criteria, specifications and control measures.

Need help with your BM522 network diagram and critical path?

Task 2 carries the most marks, so run the forward and backward pass carefully: activities 9 and 10 both follow approval (activity 4) and feed configuration with the procurement chain (5–8), so compare those paths before naming the critical path, and remember activity 16 waits for both 10 and 15. Keep your Gantt dates on working days from 11 January 2027 so the milestones match the network diagram, and make the WBS deliverable-based rather than a copy of the task list. Our project management assignment help can check your critical path and WBS, and our report writing help suits the 1,500-word structure. Browse more Buckinghamshire New University assignment briefs.

Shared with
Students Assignment Help UK Editorial Team

Students Assignment Help UK Editorial Team

A student shared this brief with our team; personal details have been removed. Our editorial team works on tasks like this and can guide you on how to approach it.

Answer
img-blur-answers

Facing Issues with Assignments? Talk to Our Experts Now!Download Our App Now!

Have Questions About Our Services?
Download Our App!

Get the App Today!

QRcode