- Person-centred Approaches in Health and Social Care Settings Assignment: Guidance Document and Consent Briefing Report | LCPS
- BEM1083DA Business Environment and Organisational Strategy Assessment 2 2026/27: Effective Project Manager Presentation | University of Exeter
- Principles of Business and Resource Management for Leaders of Adult Social Care Assignment Brief 2026 (Level 5 Diploma)
- 7132PY Project Planning and Ethics Capstone Research Ethics Proposal Assignment Brief 2026 | Coventry University
- Property Law Problem Question: Easements, Licences and the Sale of Hardacre (Advise Enya)
- NUR6074 Leadership and Decision Making in Adult Nursing Assessment Brief 2026: Practice Change Presentation | Birmingham City University
- PSY4007 Introduction to Studying Psychology Portfolio Assessment Brief: Five Tasks from Perspectives to Academic Skills | Arden University
- HSO5004 Health Promotion: Challenges and Opportunities Assessment Brief 2026: Health Promotion Event and Evaluation Report | Regent College London
- CIPD Level 3 3CO01 Business, Culture and Change in Context Assessment Questions: Gearspan Ltd Case
- DL503 Land Law Assignment Brief 2026: Qualifi Level 5 Diploma in Law (Proprietary Estoppel and Case Study)
- CIPD 5LD01 Support Informal and Self-Directed Learning Assessment Brief 2026: Lux-stay Case Study
- SPY00157M Exploring Policy Research Summative Assessment Brief 2026 | University of York
- COM4024 Introduction to Academic Skills and Professional Development Assessment Brief 2026 | Arden University
- VTCT Level 4 UBT501 and UBT503 SAR Assignment Paper B Brief 2026
- CET3016 Enterprise Software Engineering Assignment 1 2026: SunMortgages Analysis and Design | Sunderland
- Unit 8204 Working in Partnership with Others and Unit 8201 Person-Centred Assessment Questions: Level 4 Diploma in Adult Care
- AP503 Working Collaboratively with Healthcare Professionals Assignment Brief 2026
- AP502 Professional Standards within Aesthetic Practice Assignment Brief 2026
- AP501 Legal and Regulatory Requirements in Aesthetic Practice Assignment Brief 2026
- 7FNCE015W Global Banking and Lending Assessment 1, 2026 | UOW
BN3017: Analyse Project Cost Revenue And Other Financial Data: Expenditure Planning & Control Assignment, UOM, UK
| University | University of Manchester(UoM) |
| Subject | BN3017: Expenditure Planning & Control |
Learning Outcome’s
1. Analyse project cost, revenue, and other financial data and the factors which determine their nature and extent.
2. Implement anticipated project financial scenarios to produce reasoned management advice.
3. Develop financial information into contractual claims, budgets, and reports.
The following information relates to the construction of traditional masonry external walling on a competitively tendered project.
- The budget rate for blockwork is £45 per m2
- The budget rate for half brick wall in facings is £67 per m2
- The budget rate for forming a cavity is £5 per m2
Do You Need Assignment of This Question
The following prices, rates, and other costs were used in compiling the budget.
- Skilled labor £16 per hour
- Unskilled labor £12 per hour
Site overheads were calculated at 10% of the estimated cost of the work undertaken
- Cost of 440 x 215 x 100mm blocks £150 per 100
- Cost of mortar £137 per m3
- Cost of facing bricks £475 per 1000
- Cost of wall ties £22 per 100
The external walling continued for four 8 hour days on-site, and one 4 hour day. At the end of the fifth day the following amount of work had been completed:
- Blockwork 300 m2
- Brickwork 250m2
The actual site overheads (supervision, scaffolding, plant, transport, etc. were established at £2,250 per day.
Buy Answer of This Assessment & Raise Your Grades
After the budget had been determined and agreed, but before the operations commenced, the firm was unable to use its anticipated workforce, and was obliged to employ labor only subcontractors, who charged £450 per 1000 for facings and £150 per 100 for blockwork (prices include forming cavity and all pointing).
The estimated costs of the two operations, taken from the original budget, are as follows:
BLOCKWORK
- Mortar .007m3 @ £150 1.05
- Blocks 10 @ £150 per 100 15.00
- Skilled labour 0.5 hours @ £16 8.00
- Unskilled labour 0.5 hours @ £12 6.00
- Overheads @ 10% of costs 3.01 £ 33.06 per square metre
FACING BRICKWORK
- Mortar .02m3 @ £150 3.00
- Bricks 60 @ £475 per 1000 28.50
- Skilled labour 1.0 hours @ £16 16.00
- Unskilled labour 0.5 hours @ £12 6.00
- Overheads @10% of costs 5.35 £ 58.85 per square metre
FORMING CAVITY
- Wall ties 4 @ 20p each 0.80
- Skilled labour 0.1 hours @ £16 1.60
- Unskilled labour .07 hours @ £12 0.84
- Overheads @ 10% of cost 0.32 £ 3.56 per square metre
The number of blocks used in the period amounted to 3500 and the price actually paid was £160 per 100.
The number of bricks used was 18000 and the price actually paid was £460 per 1000. 1400 wall tiles at a price of £25 per 100 were used.
The amount of mortar used in the period was 10m3 at a cost of £150 per m3.
Are You Looking for Answer of This Assignment or Essay
Are you looking for assignment writing help in (BN3017) Expenditure Planning & Control? Searched everywhere still not getting the relevant answers, no worries we will help you out the University Assignment help offer high-quality assignment help to all the students and learners for essay assignments, dissertation writing, thesis assessment, and all types of coursework. As a UK best assignment provider, we always assure plagiarism-free content with complete confidentiality.