BM522 Project Management CW1 Guide: Critical Path, Gantt and WBS for the Regent House Hotel Project

Published on: November 16, 2026 | Students Assignment Help UK Editorial Team | 10 views

The marks in BM522 CW1 sit mainly in Task 2, so work out the forward and backward pass by hand first, state one shortest completion time, and only then draw the network diagram and Gantt chart. Everything else in the 1,500-word report (business case, stakeholders, WBS, risks and quality) is shorter and easier to score once the schedule is right. This guide explains how to plan the report, where students lose marks and how to check your own critical path. Need a second pair of eyes? Our project management assignment help page explains the support available.

What BM522 CW1 is really asking

The BM522 Project Management CW1 Regent House Hotel brief at Buckinghamshire New University gives you the project and the 18-activity list. Your job is to plan it like a project manager, not to redesign the hotel’s check-in system.

The report has six tasks with different weightings. Task 2 (network diagram, critical path and Gantt chart) carries 25 marks, Task 3 carries 20, Task 1 carries 15 and Task 4 carries 10, so spend your time in proportion.

A sensible word and effort split

Task Marks Suggested words Where the marks come from
1. Business case and objectives 15 300 to 350 Clear need, three SMART objectives, constraints, justified approach
2. Network diagram and Gantt 25 200 to 250 plus visuals Correct ES, EF, LS, LF, critical path and completion time
3. Stakeholders 20 250 to 300 Five or more stakeholders, power and interest, conflicts, plan in appendix
4. WBS 10 100 plus diagram Deliverables rather than a chronological list
5. Risk analysis see brief 200 to 250 Scored register and mitigation for the five highest risks
6. Quality see brief 150 to 200 Five requirements with acceptance criteria and controls

Check the exact marks and word guidance in your own brief, because the split above is only a planning aid. Diagrams, tables and appendices are usually treated differently from the main word count, so confirm this in your module handbook.

Want a model layout to compare with yours? Our BM522 CW1 sample extract is for reference only and uses illustrative figures.

How to calculate the critical path without mistakes

The brief tells you to use the day 0 convention, so the first activity has an early start of 0. Work through the list in this order.

  1. Forward pass. Early finish equals early start plus duration. Where an activity has several predecessors, its early start is the largest of their early finishes.
  2. Backward pass. Start from the last activity, set its late finish equal to its early finish, and subtract durations going back. Where an activity feeds several successors, its late finish is the smallest of their late starts.
  3. Float. Late start minus early start. Zero float means the activity is critical.
  4. Trace the path. Follow the zero-float activities from start to finish and confirm they form one unbroken chain.
  5. State the answer. Write the critical path in sequence and give the shortest completion time in working days.

The three merge points that trip students up

Look for activities with more than one predecessor, because that is where wrong early starts appear. Configuration (activity 11) waits for the contract sign-off and for the technical assessment and process design. Internal testing (activity 15) waits for integration, the compliance review and the kiosk installation. Staff training (activity 16) waits for both the process design and the internal testing.

In each case, take the latest finishing predecessor, not the first one you meet. A quick test is to ask which predecessor would delay the merge activity if it slipped by a day.

It also helps to notice that two paths run in parallel after approval: the procurement chain and the assessment-and-design work. Compare their total lengths before naming the critical path, and say in a sentence why the longer one controls the schedule.

Turning the calculation into a Gantt chart

Use the same working-day arithmetic as the network diagram. Start on the project date given in the brief, count working days only (Monday to Friday), and ignore public holidays because the brief says to. The finish date on your chart must match the completion time on your network diagram, otherwise a marker will see two different answers.

  • Show each activity as a bar with its predecessor links.
  • Mark critical activities in a different colour and explain the colour in a key.
  • Add milestones such as approval, contract signature, end of testing and rollout.
  • Check that the chart finishes inside the six-month window the brief allows.

Mark-maximising checklist

  • Every activity from the brief appears in the network diagram with duration, ES, EF, LS and LF.
  • The critical path is highlighted and written out as a sequence of activity numbers.
  • One shortest completion time is stated, in working days and as a calendar date.
  • The Gantt chart dates agree with the network diagram.
  • Three objectives are specific, measurable, achievable, relevant and time-bound.
  • At least five stakeholders sit on a power and interest grid, with different strategies for each.
  • The WBS is numbered and built from deliverables.
  • The five highest risks have a score, an owner and an action.
  • Each quality requirement has an acceptance criterion and a control measure.
  • Referencing follows the style your module requires, with a reference list.

Common mistakes to avoid

  • Copying the activity list into the WBS. A WBS groups outputs, not a timeline.
  • Using calendar days in the Gantt chart when the durations are working days.
  • Giving two different completion times in the report and the chart.
  • Choosing the wrong predecessor at a merge point.
  • Writing generic risks such as “delay” with no cause, score or action.
  • Treating the business case as a description of the hotel rather than an argument for the project.

A simple order of work

Students who start with the diagram often redraw it three times. A calmer order is to build the activity table in a spreadsheet, run the forward and backward pass, and check the totals before opening any drawing tool.

Next, write the Task 1 business case, because the objectives and constraints tell you what the schedule has to achieve. Then draw the network diagram and Gantt chart from your table, add the stakeholder grid and WBS, and finish with the risk register and quality table.

Leave at least a day at the end to read the report as a marker would. Check that every number in the text matches the table it came from, that the dates agree across tasks, and that the six tasks appear in the order the brief sets out.

Common student worries

Many students are anxious about the software. MS Project is allowed, but it is not the marking focus: a hand-calculated table plus a clean chart from any approved tool is better than a polished chart that disagrees with the numbers. Others worry about word count. Put the long tables in the body only when they are needed, and keep the written commentary tight.

If you are short of time, plan backwards from the deadline, build the schedule first and leave the stakeholder and quality tables until the end. For wider planning support, see our report writing help page, and for how we work, read about our service.

FAQs

Which activities are on the critical path?

Work it out from your own table rather than copying a list. The critical path is the unbroken chain of zero-float activities from the first to the last, and its total length is the shortest completion time.

What does the day 0 convention mean?

It means the first activity starts at time 0, so an activity that lasts two days finishes at day 2. Use it consistently in every ES, EF, LS and LF value.

Do I need MS Project for the Gantt chart?

The brief names MS Project or an approved tool. Check your module guidance for what is acceptable, and make sure the exported chart is readable in the report.

How many stakeholders do I need?

At least five, mixing internal and external groups. Explain their expectations, concerns, influence and any likely conflicts, not just their names.

Should the WBS follow the activity order?

No. Group the work by deliverable, such as procurement, system build, compliance and launch, and number the levels clearly.

Is it acceptable to use AI tools for this coursework?

The brief states the AI category for this assessment, so follow it exactly and declare any use as your university requires. Planning guides and reference samples are study aids, and the work you submit must reflect your own understanding.

If you would like tailored feedback on your own schedule, risk register or WBS, submit your assignment details and our team will respond with options.

Written by
Students Assignment Help UK Editorial Team

Students Assignment Help UK Editorial Team

Our editorial team works with students in the UK and sees the questions they ask most often. This guide is built from those real queries: where students get stuck, what markers look for and how to plan the work step by step.

Latest Posts

UPTO 35% DISCOUNT

Get Your Assignment Completed At Lower Prices

Plagiarism Free Solutions
100% Original Work
24*7 Online Assistance
Native PhD Experts
Hire a Writer Now

Facing Issues with Assignments? Talk to Our Experts Now!Download Our App Now!

Have Questions About Our Services?
Download Our App!

Get the App Today!

QRcode